4. Commissioning
4−13
Festo P.BE−CPX−CMAX−SYS−EN en 0908NH
6. Parameterise application data and download it to the
CMAX:
Mass
Supply pressure
Mounting position
This application data is the basis for configuring the con
troller.
7. Set the other parameters (e.g. software end positions,
record list, ...) and download them to the CMAX.
8. Switch on the compressed air supply.
9. Carry out the movement test:
10. Only with incremental position
measuring system: Carry
out homing.
11. Carry out identification run.
12. Carry out a test run.
After commissioning the positioning system (see supple
mental CMAX communication profile" description):
13. Configure the CPX bus node or CPX−FEC.
14. Check the control of the positioning system with the
CMAX.