4 Planning and installation – Pellet bunker
72
INSTALLING THE SLOPING FLOOR
SUPPORTS
A) 155 cm
B) max. 75 cm
1. Firmly screw the sloping floor supports (1) to the floor of the pellet
bunker.
2. Note the necessary spacing as shown in Fig. 4/61
The sloping floor supports have been installed.
I
NSTALLING THE BEARING
BEAMS
3. Bolt the bearing beams (1) short side up onto the sloping floor
supports (2).
4. To provide additional support for the bearing beams, bolt
additional squared timbers to the walls (3).
The bearing beams have been installed.
Figure 4/61 - Installing the sloping floor supports
B
A
1
Figure 4/62 - Installing the bearing beams
1
2
3