9.13.7 Commissioning
Under the commissioning menu it is possible to adjust the several parameters:
Screed Drying:
• Circuit 1 setting temperature
• Circuit 2 setting temperature
• Start screed drying
Pump down procedure:
• Duration
• Start pump down
Air purge procedure:
• Duration
• Start air purge
Unit test run:
• Duration
• Mode (not available for heating only)
• Start test run
9.13.8 About
In this section of the LCD controller it is possible to nd the following information:
System information:
• Unit type
• Unit capacity
• Serial number
• Controller rmware
• Indoor PCB rmware
• Language package
• Refrigerant
Contact information:
It is possible and recommendable
to ll this information providing a
contact phone to the user.
UNIT CONTROLLER (PC-ARFH2E)
PMML0575 rev.2 - 03/2022
230