Space and airflow requirements
A fully populated server is heavy. Hewlett Packard Enterprise recommends removing the external chassis components before
installing the server into a rack.
Hewlett Packard Enterprise recommends having at least two people to install the server into the rack: One person to support the
server weight, and the other to align the chassis into the rack rail slots.
Before you perform this procedure, make sure that you have a T-15 Torx screwdriver available.
ProcedureProcedure
1. Grasp the tray notch to slide the tray out of the rack.
2. Place the server on the tray.
Verify that the front panel of the server is align with the front of the tray.