Figure 4-1 Bottom pipe routing scenario
(1) Inverted trap (2) Oil trap (3) Tilted gas pipe (4) Tilted liquid pipe
Figure 4-2 Top pipe routing scenario
(1) Inverted trap
(2) Oil trap (3) Tilted gas pipe (4) Tilted liquid pipe
4.1.2 Indoor Unit Installation Requirements
● If the actual server total load for each smart cooling product is less than 10%
of rated cooling capacity or the equipment room is not properly sealed, the
humidity in the equipment room may be too high, which is not a product
quality issue and should be dealt with by adding a
dehumidier.
● Do not install the smart cooling product near a noise-sensitive place such as an
oce or a conference room.
NetCol5000-A050 In-row Air Cooled Smart Cooling
Product
User Manual 4 Installation
Issue 08 (2021-09-17) Copyright © Huawei Technologies Co., Ltd. 34