Figure 4-27 Leveling and xing the cabinet
Testing the Insulation and Installing the Front Pallet
1. Testing the insulation of the cabinet.
a. Set the multimeter to read mega ohms.
b. Measure the resistance between the M12x35 bolt and the ground bolt of
the rack, the measured resistance is more than
ve mega ohms.