Figure 4-224 Removing the spring washer, at washer, and bolt
----End
Placing the Cabinet
Precautions
Pay attention to the following points when placing a cabinet:
● Expansion bolts have insulation washers. Install all insulation parts correctly
to ensure that the cabinet is insulated from the ground before cables are
connected.
● To reduce the stress between expansion bolts and the cabinet,
x the
expansion bolts on diagonal lines.
Procedure
Step 1 Move the cabinet into the outline drawn in the installation area. (The cabinet's
casters enable you to move the cabinet without additional tools.)
Step 2 Use a right angle to align the outer surface of the cabinet with the outline, as
shown in Figure 4-225.
HUAWEI NetEngine 8000 F
Hardware Guide 4 Hardware Installation and Parts Replacement