Figure 4-229 Securing the cabinet
----End
Testing the Insulation Performance
Insulation Requirement
The impedance between the cabinet and ground must be larger than 5 Mohm.
Procedure
Step 1 Set the multimeter measurement mode to Mohm and measure the impedance
between the bolts and cabinet, as shown in Figure 4-230.
HUAWEI NetEngine 8000 F
Hardware Guide 4 Hardware Installation and Parts Replacement
Issue 05 (2023-03-31) Copyright © Huawei Technologies Co., Ltd. 570