Step 6 Install the top cover from the connection box.
Figure 5-17 Installing the top cover from the connection box
Step 7 Move the top cover of the PG box to the assembly position and tighten the PG
connector.
Figure 5-18 Reinstalling the PG box cover
----End
5.2.3.3.2 10 kVA
Context
Use diagonal pliers to cut o the port bae plates based on the actual situation.
Figure 5-19 Port bae plates
(1) Port bae plates
Step 1 Switch o the upstream AC circuit breaker for the UPS.
Step 2 Remove the top cover from the connection box.
UPS2000-H-(6 kVA-10 kVA)
User Manual 5 Installation and Cable Connection
Issue 03 (2023-08-20) Copyright © Huawei Digital Power Technologies Co., Ltd. 68