Figure 5-29 Installing the top cover from the connection box
----End
5.2.3.4.2 10 kVA
Context
Use diagonal pliers to cut o the port bae plates based on the actual situation.
Figure 5-30 Port bae plates
(1) Port bae plates
Step 1 Switch o the upstream AC circuit breaker for the UPS.
Step 2 Remove the top cover from the connection box.
Figure 5-31 Removing the top cover from the connection box
Step 3 Install AC output power cables and then AC input power cables in sequence.
● Single-phase input single-phase output
a. Take out a short-circuit copper bar from the tting bag and short-circuit
L1, L2, and L3 using the short-circuit copper bar.
b. Secure the AC power cables to the wiring ports.
UPS2000-H-(6 kVA-10 kVA)
User Manual 5 Installation and Cable Connection
Issue 03 (2023-08-20) Copyright © Huawei Digital Power Technologies Co., Ltd. 72