Figure 5-39 Installing the guide rails
Step 4 Install the UPSs and batteries with mounting ears on the rack, and then install the
battery front panels.
Figure 5-40 Installing the UPSs and batteries
----End
5.3.2 Tower-Mounted Installation
5.3.2.1 Installing the UPSs and Lead-Acid Batteries
UPS2000-H-(6 kVA-10 kVA)
User Manual 5 Installation and Cable Connection
Issue 03 (2023-08-20) Copyright © Huawei Digital Power Technologies Co., Ltd. 77