Figure 5-36 Installing battery cables (four battery packs)
You are advised to purchase circuit breakers for battery cables. For details about the battery
circuit breaker specications, see 5.1.4 Power Cables.
----End
5.3 Installing a Parallel System
Prerequisites
Only single-phase and three-phase inputs support parallel connection.
5.3.1 Rack-Mounted Installation
5.3.1.1 Installing the UPSs and Lead-Acid Batteries
Procedure
Step 1 Install mounting ears on both sides of the UPS.
UPS2000-H-(6 kVA-10 kVA)
User Manual 5 Installation and Cable Connection
Issue 03 (2023-08-20) Copyright © Huawei Digital Power Technologies Co., Ltd. 75