5.7 Installing an rPDU and rPDU Cables
Step 1 Install the rPDU in an appropriate position based on site requirements.
Step 2 Install rPDU cables.
1. Connect the rPDU ground cable to the nearest ground point on the rack.
2. Connect one end of the power cable to the rPDU wiring port.
NO TICE
If rPDU cables have been connected onsite, skip this step.
Connect cables to the rPDU based on the type of the rPDU and the silk
screen on the wiring port. The following cable connection is for reference
only.
Figure 5-65 Connection position in horizontal PDU2000-16-1PH-8/0-B1
Figure 5-66 Connection position in vertical PDU2000-63-1PH-16/8-B1
UPS2000-H-(6 kVA-10 kVA)
User Manual 5 Installation and Cable Connection