4. JUICE ULTRA installation
This chapter describes the mechanical and the electrical installation of the JUICE ULTRA.
It is recommended to install the JUICE ULTRA according the following steps and related
chapter in the following sections:
- Site configuration (see chapter 4.1.3)
- JUICE ULTRA base positioning (see chapter 4.1.4)
- Preparation of the mains power-supply cables (see chapter 4.2.3)
- Lift the JUICE ULTRA with a crane on the JUICE ULTRA base
- Screw the JUICE ULTRA via 4x M12x30 screws and 32mm washers together to the
JUICE ULTRA-base. The screws are to be tightened with a torque of 90Nm.
- Connect the mains power-supply (see chapter 4.2.4)