Table 22: Deployment Checklist (continued)
DatePerformed ByFor More InformationItem or Task
“QFX5110 Clearance Requirements for Airflow
and Hardware Maintenance” on page 55
Clearance Requirements for Airflow and
Hardware Maintenance for a QFX5100 Device
Clearance Requirements for Airflow and
Hardware Maintenance for a QFX3600 or
QFX3600-I Device
Clearance Requirements for Airflow and
Hardware Maintenance for a QFX3500 Device
Clearance Requirements for Airflow and
Hardware Maintenance for EX4300 Switches
Plan rack or cabinet location, including
required space clearances.
Secure the rack or cabinet to the floor
and building structure.
Cables
“Cable Specifications for QSFP+ and QSFP28
Transceivers” on page 62
“Cable Specifications for Console and
ManagementConnections for the QFX Series”
on page 64
Acquire cables and connectors:
Determine the number of cables
needed based on your planned
configuration.
Review the maximum distance
allowed for each cable. Choose the
length of cable based on the
distance between the hardware
components being connected.
Plan the cable routing and
management.
Related
Documentation
QFX5110 Site Preparation Checklist on page 43
Site Preparation Checklist for a QFX5100 Device
Site Preparation Checklist for a QFX3600 or QFX3600-I Device
Site Preparation Checklist for a QFX3500 Device
Site Preparation Checklist for EX4300 Switches
QFX5110 Rack Requirements
QFX5110 switches are designed to be installed on four-post racks.
Rack requirements consist of:
Rack type