Introduction
The Spraytec system should initially be commissioned by Malvern trained
personnel. This appendix shows how to re-install the system, typically required
under the following circumstances:
.
Moving the instrument if the system has to be moved from one labora
-
tory to another, read the information in this appendix to reconnect the sys
-
tem correctly.
.
Changing the computer it may be company policy to upgrade comput
-
ers periodically. Detail is given on the procedure.
Only install the system in a suitable environment as detailed in Appendix C - Site
Requirements.
Moving the instrument
Handle the instrument carefully and do not subject it to any strong physical
shock.
#
Warning!
Short distance movements
If moving the system just within a room:
.
Power off all components and accessories.
.
Disconnect the mains power cable from the Spraytec.
.
The instrument can be moved with the Transmitter and Receiver mounted
on the X-bar, so long as this is done with care as described in the warning
above.
APPENDIX E
Spraytec Page E.1
Use proper lifting techniques and at least two people to avoid back
injury. One person must support each module on the X-bar. Always lift
the instrument by holding it under its base.
Never lift an instrument by precision parts such as the lens, or by its
covers.