Maintenance overview
5.2 Maintenance plans
16.11.2018
Maintenance manual 3 302 756 en 5 - 11
GMK6400
Maintenance work on the SUPERSTRUCTURE:
Monthly / after 250 oper. hrs.
Hoists
– Support for block – Checking the sheaves à p. 8 - 13
Slewing bearing
– Checking the bolts à p. 8 - 23
Hydraulic system
– Cleaning the magnetic rods à p. 8 - 46
Main boom
– Lubricating the telescopic sections à p. 8 - 66
– Checking the sheaves à p. 8 - 70
Hoist ropes
– Lubricating the hoist rope à p. 8 - 73
Hook blocks
– Checking the sheaves à p. 8 - 91