Distributed I/O system
System Manual, 12/2016, A5E03576849-AG
197
Commissioning
10
10.1
Overview
Introduction
This section includes information on the following topics:
● Commissioning the ET 200SP distributed I/O system on the PROFINET IO
● Commissioning the ET 200SP distributed I/O system on the PROFIBUS DP
● Startup of the ET 200SP distributed I/O system with empty slots
● Removing/inserting the SIMATIC memory card
● Operating modes of the CPU
● CPU memory reset
● Reassigning parameters during operation
● Identification and maintenance data
Commissioning requirements
Note
Performing tests
You must ensure the safety of your plant. You therefore need to run a complete functional
test and make the necessary safety checks before the final commissioning of a plant.
Also allow for any possible foreseeable errors in the tests. This avoids endange
ring persons
or equipment during operation.

Table of Contents