Safety, approvals, EMC
9.2 Test voltage
SITOP UPS1600 / BAT1600 / UPS1100
254 Equipment Manual, 07.2021, A5E37775406-11-76
9.2 Test voltage
Figure 9-1 Test voltage diagram
Only applicable for UPS1600 with PROFINET (-2AY0).
Only the manufacturer can perform the type test and production test; users can also perform
the field test.
Preconditions for performing the field test:
Test (A)
• Connect the input, output, battery connection BAT and signaling contact with one another
and measure with respect to PE.
Test (B)
• Connect all PROFINET cables and measure with respect to PE (input, output, battery
connection BAT signal connector and PE are connected with each other)
Table 9- 1 Test voltage
Input, output, BAT ↔ PE (A)
Tripping current for DC measurement: 0
mA
Tripping current for AC measurement: < 100 mA