Varec, Inc. 13
Installation Checklist
When installing a 2500 ATG system on a bolted tank, complete each installation step below.
Check off a step when it is complete. Refer to “Installation Schematics” on page 21 for overall
dimensions.
Table 3: Bolted Tank — Installation Checklist
Cone Roof Tank with Internal (Floating Roof) Pan and Floatwell
Order Code T02, T12
Installation parts supplied include:
90° Elbow assembly (x2)
Gauge 'U' bolt kit
Support bracket (x6)
gauge head and tape/cable
Float
Tape cable connectors
Figure 7: Cone Roof Tank with (Internal Floating)
Roof Pan and Floatwell
Installation Checklist
When installing a 2500 ATG system on a Cone Roof Tank with Internal (Floating Roof) Pan and
Floatwell, complete each installation step below. Check off a step when it is complete. Refer to
“Installation Schematics” on page 21 for overall dimensions.
Step Description Complete
1
Tank Roof Entry - Internal Pan (Floating Roof)” on page 24
2
“Installing Anchors and Guide Wires” on page 25
3
“Installing Support Brackets & Pipework” on page 27
4
“Installing a Gauge Head at Grade Level” on page 28
5
“Float installation on an Out-of-Service Tank” on page 30
6
“Connecting the Tape to the Float” on page 30
7
“Feeding the Tape to a Gauge Head Located at Grade Level” on page 34
8
“Install Tape in the Gauge Head” on page 35
9
“Reset the Counter” on page 40
10
“Calibrate the Counter” on page 41
11
“Initial Lubrication” on page 42
12
“Install a Transmitter and Replace all Covers” on page 42
13
“Initial Operation” on page 43

Table of Contents