Table 5: Cone Roof Tank and Internal (Floating Roof) Pan: No Floatwell — Installation Checklist
Tank Top Mounting
Order Code T04, T14, T24, T32
Installation parts supplied include:
• Gauge 'U' bolt kit
• Guide Wire bottom anchor
• Guide Wires
• gauge head and tape
• Float
• Guide Wire top anchors (x2)
• Tape connectors
Figure 9: Tank Top Mounting
Installation Checklist
When installing a 2500 ATG system on a cone roof tank, complete each installation step below.
Check off a step when it is complete. Refer to Section “Installation Schematics” on page 21 for
overall dimensions.
Step Description Complete
1
“Tank Roof Entry - Internal Pan (Floating Roof)” on page 24
2
“Installing Support Brackets & Pipework” on page 27
3
“Installing a Gauge Head at Grade Level” on page 28
4
“Connecting the Cable to a Floating Pan” on page 33
5
“Feeding the Tape to a Gauge Head Located at Grade Level” on page 34
6
“Install Tape in the Gauge Head” on page 35
7
“Reset the Counter” on page 40
8
“Calibrate the Counter” on page 41
9
“Initial Lubrication” on page 42
10
“Install a Transmitter and Replace all Covers” on page 42
11
“Initial Operation” on page 43
Step Description Complete
1
Section “Tank Roof Entry - Cone Roof Tank” on page 23
2
Section “Installing Anchors and Guide Wires” on page 25
3
Section “Installing a Roof Reading Gauge Head” on page 29
4
Section “Float installation on an Out-of-Service Tank” on page 30