Chapter 4 Settings and Test
23
Chapter 4 Settings and Test
Guide:
Wiring connection
Power on
System SettingsSettings
Group Selection
Parameters Settings
Start to test
Extended Function
Calibration
Shutdown
Precautions before starting the comprehensive measurement system
The comprehensive test system includes AN9651BV3 and AN9651CV3. Before turning on,
please make sure that the comprehensive test system has been connected to a sufficient capacity
and stable AC power supply. In order to reduce the impact of the inrush current (Inrush Current)
on the comprehensive measurement system at the moment of startup, it is recommended that the
startup sequence is to turn on the power switch of the whole machine (front panel air switch), and
then turn on the power switch of the electrical safety comprehensive analyzer.
4.1Wiring connection
Connect the wire according to the following sequence:
Connect test box and GB clamp connect input power of DUT connect input power of the
instrument connect DUT to test box.
4.1.1 Connect Test Box and GB clamp
Connect the wire as shown in Figure 4-1-1: