8.2 Setting the spread rate - Performing the calibration test
1. Enter the desired spread rate on the control terminal.
2. Perform a calibration test to determine the calibration factor.
The spread rate must be set for
Seed
Fertiliser (optional)
Perform a calibration test after setting the desired spread rate!
1. Perform a calibration test for seed.
2. Perform a calibration test for fertiliser.
When spreading seed and fertiliser at the same time, the spread rate
is limited.
15 km/h:
Maximum seeding rate: 250 kg/ha
Minimum seeding rate:. 2 kg/ha (1 dosing unit)
Maximum fertiliser rate: 80 kg/ha
8.2.1 Calibration test
The calibration test checks whether the preset spread rate matches
the actual spread rate.
Always carry out a calibration test:
when changing the seed type/fertiliser
if the seed type is identical, but size grain, grain shape, specific
weight and dressing are different
after exchanging the dosing rollers
WARNING
Never step between the machine and the exact harrow before th
e
stop tap is closed which blocks the hydraulics of the exact har-
row.
When spreading the seed and fertiliser at the same time, carry out
one calibration test each for the seed and fertiliser separately.
Gears not used for the calibration test should be set to po-
sition 0.
Whenever possible calibrate and set the seed rate after the journey
to
the field with the filled seed hopper.
This ensures a more accurate seed rate.