8. Pull out the scraper rope by hand over the free wheel of the rope drum.
If the thumb button (8) of the radio system is not actuated, the rope
can be pulled out via the free wheel of the rope drum.
9. Use the scraper shovel (7) to pull a ramp of sand or gravel in front of
the feeder (6).
The machine must be aligned so that the sand pile is always
centred in front of the feeder (6).
10. Pull the scraper shovel (7) manually behind the sand pile.
11. Operate the thumb button (8) of the radio system and keep it pressed.
The rope is wound up by the winch. The scraper shovel (7) is pulled
through the sand pile and loaded.
Depending on the position of the scraper shovel (7), you can
influence the amount of sand to be transported.
12. Pull the filled scraper shovel (7) over the ramp to the tipping point of the
feeder (6).
13. Switch off the winch by releasing the thumb button (8).
14. Empty the scraper shovel (7) into the feeder (6).
15. Repeat the process until the feeder (6) is filled.
NOTE
The feeder is suitable only for filling with sand or gravel. You must not add
any binding agent or water to the feeder.
There is a risk of heavy soiling. Cleaning is only possible with great effort.
A dirty feeder can have a too high total weight. The function can be
impaired (up to non-functioning!).
16. Pull the "Raise/lower feeder" lever horizontally out of its locking device
and swivel it upwards until the material slides into the mixing and
delivery vessel.
17. Fill the mixing and delivery vessel to half its capacity and then swivel
the feeder down again using the "Raise/lower feeder" lever.