EasyManua.ls Logo

Dorr EcoBell2 SL EC - 9.6 Working on paint pipe; 9.6.1 Removing paint pipe; 9.6.2 Checks on removed paint pipe; 9.6.3 Disassembling the paint pipe

Dorr EcoBell2 SL EC
156 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Operating Manual
© Dürr Systems AG
128 / 156
EcoBell2 SL EC
- Rotating Atomizer with External Charging
Faults
Document No.: MRA00001EN
Version:: 07 As of:: 01/2020
9.6 Working on paint pipe
The paint pipe is lodged in the valve block.
Before removing the paint pipe, the following work should be done:
- Valve block removed
- Shaft detent removed
- Chuck removed
- Main needle valve removed
- Nozzle removed
- Contact ring removed.
9.6.1 Removing paint pipe
Loosen the three screws at the bottom of the paint pipe.
Fig. 81: Screws on the paint tube
1 Screws
Pull out the paint tube from the valve block.
9.6.2 Checks on removed paint pipe
- Damage to the paint pipe, especially by contact with the turbine
shaft
- Cleanliness of bores and channels
- Cleanliness and functioning of the contact for the high voltage
(ball).
9.6.3 Disassembling the paint pipe
The nozzle holder of the paint pipe is unscrewed in the following way:
Set one open-end wrench on the hexagon of the paint pipe.
Set second open-end wrench on the nozzle holder.