Express Install for File OE Release 7.1 or higher
225
NAS Install Options
EMC CONFIDENTIAL
The system prompts you to select the number of fibre switches to use
(Figure 149).
Figure 149 Number of Fibre Channel switches screen
17. Enter the number of switches and press Enter.
The system prompts you to enter information for switch 1 (Figure 150).
Figure 150 Fibre Channel switch 1 settings
18. Enter the Fibre Channel switch information, tab to OK, and press Enter. Get the
FC switch information from the “FC/FCoE cabling worksheet” on page 273.
The system prompts you to enter switch 2 information (similar to Figure 150).
19. If you selected to use more than one FC switch for the new array, the system
prompts you to enter information for the next switch (similar to Figure 150). Enter
the information, tab to Ok, and press Enter. Repeat for each FC switch.
20. If the VNX array has only two frontend ports on each SP, the system prompts you
for confirmation. If you get this prompt, go to step 23 on page 227.