3. MECHANICAL INSTALLATION
TOOLS REQUIRED
The tools required are indicated below.
7-19
Spanner
3, 8
Phillips screwdrivers
Level Angle grinder
Screw clamp
Welder (for steel rack
to be welded on)
5, 6.5
Drill bit for metal
M8
Thread cutter (for
screw-on steel rack)
TORQUE ADJUSTMENT -comply with fastening torque indicated in
the figure. E.g.: Spanner 7 set at 2.5 Nm
7
2.5 Nm
3.1 INSTALLING THE FOUNDATION PLATE
The product must be installed with the foundation
plate.
i
Before proceeding, the cable conduits must be laid.
1. Assemble the foundation plate.
2. Make the hole in the ground.
- Make sure that the cable conduits protrude by
approximately 15 cm, in the correct position with
respect to the gearmotor and fill will concrete.
3. Place the plate at the centre of the foundation,
leaving its surface uncovered.
- Clean any concrete from the surface of the plate
and the nuts with washers so that they can be
subsequently adjusted.
- Check the plate is horizontal using a spirit level.
4. Wait for the concrete to set.