BX900 S2 Upgrade and Maintenance Manual 115
Connection blades
8.2.1.5 Concluding steps
Perform the following procedures to complete the task:
Ê If applicable, install the SFP transceiver modules as described in section
"Installing SFP+ transceiver modules" on page 127
Ê Connect the external cables to the connection blade.
Ê If applicable, integrate the connection blade in a connection blade stack as
described in section "Connection blade stacking" on page 137.
I This step only applies to the connection blade GbE Switch/IBP
36/8+2 (SB11).
Ê If applicable, close the rack door as described in section "Closing the rack
door" on page 60.
Ê Configure the connection blade settings as described in section "Configuring
connection blade settings" on page 75.
Ê Create a backup copy of the connection blade settings as described in
section "Saving connection blade settings" on page 76.
8.2.2 Removing single-width connection blades
8.2.2.1 Required tools
Preliminary and concluding steps: tool-less
Removing connection blades: tool-less
8.2.2.2 Preliminary steps
Before removing a single-width connection blade, perform the following steps:
Upgrade and Repair Units (URU)
average hardware task duration: 5 minutes
average software task duration: 10 minutes