DIRECTION 5750007-1EN, REV. 1 LOGIQ E10 BASIC SERVICE MANUAL
8 - 344 Section 8-11 - Front End Acquisition / Card Cage parts replacement
Calibration and adjustments
No calibrations or adjustments are needed after this part replacement.
Verification
Perform the following steps to verify that the product is functioning as intended after this replacement:
1.) Verify that all screws that you removed earlier have been installed.
2.) Connect cables and Probes removed earlier.
3.) Power up the system to verify that it operates as intended.
Functional Checks
Perform the following functional checks to confirm the system is operational before returning the system
to the customer.
5. Re-install all Covers removed.
Table 8-356 Light Block (Hard Drive/Network Status) replacement Functional
Checks
See:
Section
Functional Check Debrief Script
4-2-3 Power ON/Boot Up
LOGIQ E10 Basic Service Manual, Direction
5750007-1EN, Rev. 1. Equipment passed all
required checks and is ready for use.
4-2-7 Probe/Connectors Checks
4-2-7 B-Mode Checks
Verify Network Activity lights emit through
the Front Cover
4-2-4 Power SHUT DOWN
Table 8-355 Light Block (Hard Drive/Network Status) replacement
Steps Corresponding Graphic