9.3.3 Identification
Label the product with the following data:
Date of decommissioning
Internal machine number/name
Additional data as per internal guidelines
9.4 Recommissioning
For recommissioning, follow the steps described for commissioning.
After cleaning work on the product or a downtime of one to four weeks,
carry out the following jobs:
Check the lubrication system Ü2111
Check lubrication film on rails and racks and pre-lubricate if necessary
ü
û
If the machine downtime is longer than four weeks, carry out the following
jobs:
Pre-lubricate rails and racks Ü2137
Decommissioning, storage
OPERATING MANUAL FlexxPump4N Lubrication