6. In the Data Migration Jobs Options dialog box (Figure 93 on page 158), specify the job attributes
as follows:
1. Under Scheduling Type, select one of the following:
Click Start Now to start the job immediately.
Click Schedule for Later, and then enter a Start Time and Start Date.
Click Serial Schedule Jobs, and then assign a priority (1256) in the Job Priority box,
where a lower value indicates that the job is scheduled earlier than jobs configured with
higher values. For details on Serial Schedule Jobs, see Starting serial scheduled
jobs on page 163.
2. In the Job Description box, enter a user-defined name to describe this data migration job.
3. In the Group Name box, select a job group name from the list. The group name makes it
easier to view the job status on a group basis.
4. In the IO Size box, select either one of the default I/O sizes, or enter a custom value.
7. To save the data migration job options, click Apply or, to abandon changes to this data migration
job, click Cancel.
Starting serial scheduled jobs
If the individual or batch data migration job you created was configured as a Serial Schedule Jobs
scheduling type on the Data Migration Jobs Options dialog box (Figure 96), the job is listed on the
Active Data Migration Jobs page. The Status column shows the job as Serial Scheduled.
To start a serial scheduled job:
1. Open the Serial Data Migration Jobs Options dialog box using one of these options:
On the Wizards menu, click Serial Schedule Job(s).
Right-click a serial scheduled job, and then click Start the Serial Schedule. This option imme-
diately starts the selected job, unless there are other jobs configured with a lower priority that
must complete migration first.
The Serial Data Migration Jobs Options dialog box opens, as shown in Figure 96.
Figure 96 Serial Data Migration Jobs Options
.
2. Under Scheduling Type, click either Start Now or Schedule for later.
3. If you choose Schedule for later, enter the Start Time and Start Date.
4. To save your settings, click Apply.
5. When prompted for a security password, enter migration.
MPX200 Multifunction Router 163

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the HP StorageWorks 6400/8400 - Enterprise Virtual Array and is the answer not in the manual?

HP StorageWorks 6400/8400 - Enterprise Virtual Array Specifications

General IconGeneral
BrandHP
ModelStorageWorks 6400/8400 - Enterprise Virtual Array
CategoryStorage
LanguageEnglish

Related product manuals