Figure 4-11 Placing the cabinet
Leveling the cabinet and testing the insulation
1. Leveling and
xing the cabinet.
a. Remove the four adjusting bolts attached on the bottom enclosure frame,
install them on the adjusting nuts.
b. Check whether the cabinet is horizontal or vertical by using a spirit level
and a plumb line respectively.
c. If the cabinet is not horizontal, adjust the adjusting bolts by using a
socket wrench.
d. When the cabinet is horizontal, fasten the four expansion bolts to 45
N·m.