Item Requirements
Door and
windows
The door of the equipment room should be 2 m (6.56 ft) high
and 1 m (3.28 ft) wide. One door is enough. Seal the doors and
windows with dustproof plastic tape. Use double-pane glass in
the windows and seal them tightly.
Wall surface
treatment
Paste wallpaper on the wall or apply at paint. Do not use
pulverized paint.
Cable trays Use cable trays to arrange cables. The inner faces of the cable
trays must be smooth. The reserved length and width of the
cable trays, and the number, position and dimensions of the
holes must comply with the requirements of device
arrangement.
Water pipe Do not pass service pipes, drainpipes, and storm sewers through
the equipment room. Do not place a re hydrant in the
equipment room, but place it in the corridor or near the
staircase.
Internal
partition wall
Separate the area where the equipment is installed from the
equipment room door. The partition wall can block some outside
dust. As shown in Figure 4-285.
Installation
position of
the air
conditioner
Install air conditioner vents so that the air does not blow directly
on equipment.
Other
requirements
Avoid the proliferation of mildew, and keep out rodents (like
mice).
Figure 4-285 Internal partition wall inside the equipment room
Equipment Room Environment
HUAWEI NetEngine 8000 F
Hardware Guide 4 Hardware Installation and Parts Replacement
Issue 05 (2023-03-31) Copyright © Huawei Technologies Co., Ltd. 643