4.2 Inspection Items and Schedule
4-3
4. Maintenance and Inspection
4.2 Inspection Items and Schedule
Follow the maintenance inspection schedule below.
It is assumed that the equipment is operating 8 hours per day.
If the equipment is running continuously night and day or otherwise running at a high operating
rate, inspect more often as needed.
Slider type
*Stainless steel sheet life guideline: 5,000km
Inspection period
External
inspection
Internal
inspection
Greasing
Ball screw Guide
Start of work inspection
- - -
1-month inspection
- - -
3-month inspection
- -
3-month inspection on
- -
Grease supply timing
(Guideline) dependent
6-month inspection
Every 6 months thereafter
Grease supply timing (Guideline)
Maximum operating speed [mm/s]
Grease supply timing (Guideline)
Operation distance Months
0 to 750 or less 1,250km
12 months
750 to 1500 or less 2,500km
1500 to 2200 5,000km

Table of Contents