Goodrive300-LIFT series inverter Commissioning guidelines
-76-
7 Commissioning guidelines
7.1 What this chapter contains
This chapter describes the commissioning guidelines for GD300L inverters special for lifts.
The commissioning process is as follows.
Start
Ensure the wiring between
the controller and inverter is
correct.
Set basic parameters.
End
Execute motor parameter
autotuning.
Adjust maintenance running
parameters.
Adjust S-curve parameters
for normal running.
Adjust comfortability.
Adjust the lift leveling
accuracy.
Debug the running mode.
Figure 7-1 Commissioning process