RADWIN 5000 Installaon Guide
August 2023
83
2.18.1 LFF and SFF Units
1. Align the unit horizontally (in azimuth):
a. Swivel the unit 90o to the le slowly, 180o to the right, and then 90o back towards the base staon.
Figure 105: Swivel horizontally (SFF unit shown)
b. While swiveling the unit, listen to the buzzer beep sequence unl opmal alignment is achieved (3
beeps and a pause, as shown below).
2. Repeat the above in elevaon.
Figure 106: Swivel vercally (LFF unit shown)
3. Once alignment is complete, ghten the bolt holding the radio on the mounng kit.