4.9 1FW6 build–in torque motors (from SW 6.1)
4-167
Siemens AG 2005 All Rights Reserved
SIMODRIVE 611 universal Description of Functions (FBU) – 04.05 Edition
4.9.2 Commissioning 1FW6 motors
The following questions must be positively answered before commis-
sioning 1FE1 motors:
Are all of the prerequisites for commissioning checked and
were the points in the checklist for commissioning checked (refer to
Chapter 4.1)?
Is the motor used a standard or an unlisted motor?
Standard motor?
In the Catalog, the motor is listed as a permanent–magnet
synchronous motor without field weakening and has an assigned
motor code (refer to Chapter A.3.3)?
When commissioning, the motor used is selected from a list.
Unlisted motor?
The motor is not included in the list of permanent–magnet
synchronous motor without field weakening and also does not
have a motor code (refer to Chapter A.3.3)?
When commissioning, the data of the motor used must be avail-
able and must be manually entered.
The necessary data is listed in the table under the index entry
”Unlisted motor – parameters for 1FW6 motor”.
Are the motor and encoder already mounted and ready to be pow-
ered up?
1FW6 motors are commissioned as follows using the SimoCom U pa-
rameterizing and start–up tool:
Readers note
Also refer to commissioning 1FE1 motors with SimoCom U in Chapter
4.8.2.
General
information on
commissioning
1FW6 motors
Commissioning
1FW6 motors with
SimoCom U