Operation Mobile Belt Loader Model 660
Operation Manual
CD397-Oper Operation - 4 - 47
Section4:Shipping
4.1ShippingPreparation
4.1.1 Fuel Tank Preparation
1. Drain fuel from fuel tank into appropriate container.
2. Disconnect fuel line at lowest accessible connection and drain fuel from fuel line.
3. Reconnect fuel lines.
4. Leave fuel cap on tank, but loosened.
4.1.2 Battery Preparation
1. Use emergency hydraulic pump to lower conveyor, if required.
2. Disconnect battery terminals from battery posts.
3. Leave battery in battery box.
4.1.3 Pre-shipping Verification
1. Make certain fuel line is connected.
2. Make certain shut-off valve on radiator is closed.
3. Make certain fuel cell drain valve is closed.
WARNING: HAZARD EXISTS WHEN REFUELING AND DEFUELING THE
TRACTOR - NO SMOKING, NO OPEN FLAMES, NO ELECTRICAL DEVICE
OPERATIONS.
NOTE:
Drain is located under unit immediately below tank.
NOTE:
On tractors so equipped, make certain in-line fuel shut-off valve is open.