Vertiv™ NetSure™ 5100 Series -48 VDC Power System Installation Manual
Proprietary and Confidential © 2023 Vertiv Group Corp.
2 Installation Acceptance Checklist
Provided in this section is an Installation Acceptance Checklist. This checklist helps ensure proper installation and initial operation of
the system. As the procedures presented in this document are completed, check the appropriate box on this list. If the procedure is
not required to be performed for your installation site, also check the box in this list to indicate that the procedure was read. When
installation is done, ensure that each block in this list has been checked. Some of these procedures may have been factory performed
for you.
NOTE!
The system is not powered up until the end of this checklist.
NOTE!
Some of these procedures may have been performed at the factory for you.
Installing the System
Relay Rack Secured to Floor (if required)
Distribution Cabinet with Module Mounting Assembly(s) Secured to Relay Rack or Equipment Rack
Optional Battery Tray Installed
Optional Battery Tray Battery Disconnect Circuit Breaker Installed
Optional P/N 559801 4-Post Flush Mounting Kit for Data Cabinets Installed (if required)
Optional P/N 560075 Field Expansion Module Mounting Assembly Spacer Kit Installed (if required)
Optional P/N 559802 Flush Mounting Kit for Relay Rack, NEBS Zone 2 Installed (if required)
Load Return Busbar Orientation Changed (if required)
Optional Lug Adapter Busbar Kits Installed
Circuit Breakers and/or Fuses Installed
Optional Transient Voltage Surge Suppressor (TVSS) Device(s) Installed
Setting Jumper and Switch Options
Jumper on System Interface Circuit Card Set
Factory Switch Setting on IB2 (Controller Interface Board) Verified
Factory Switch Setting on Optional EIB (Controller Extended Interface Board) Verified
Factory Switch Settings on SM-DU Circuit Card (located in Optional List 60 Hybrid Connection Cabinet) Verified
Making Electrical Connections
Relay Rack / Cabinet Frame Grounding Connection Made
Assemblies Comprising the Power System Frame Grounding Connection Made
Central Office Ground Connection Made
Rectifier AC Input and AC Input Equipment Grounding Connections Made
Solar Converter DC Input Connections Made (if required)