Open Breaker
Open GCB
The GCB will be opened both when the relay "Command: GCB close" de-energizes (only if "continuous pulse"
has been configured; Parameter 130), and relay "Command: GCB open" is energized. The GCB will be opened
under t
he following circumstances:
If a mains failure is detected and the mains decoupling is configured to the GCB (Parameter 159 or Para-
m
eter 160 depending on control unit)
In the operation mode STOP
If a class F2 or F3 alarm is present
Upon pressing the push-button "GCB OFF" or [GCP-32] "MCB ON" (depending on the breaker logic which
has been configured) in operation mode MANUAL
Upon pressing the push-button "STOP" in operation mode MANUAL
Upon pressing the push-button "GCB OFF" or [GCP-32] "MCB ON" (depending on the breaker logic which
has been configured) in operation mode LOAD TEST
In the event of an automatic stopping in the operation mode AUTOMATIC
[GCP-32] following the "CLOSED TRANSIT." (
make-before-break/overlap synchronization) of the MCB
[GCP-32] before the MCB is closed to the dead busbar in the case of the breaker logic "OPEN TRANSIT."
(break-before-make/changeover)
In critical mode/sprinkler operation, provided that no emergency power operation is present
[GCP-32] following the "INTERCHANGE" (mains interchange (import/export) real power control) of the
MCB
Open MCB [GCP-32]
The MCB will be opened via closing the relay "Command: MCB open" (configuration of "continuous pulse" is
not possible for the MCB). The MCB will be opened under the following circumstances:
If a mains monitoring triggers and the mains decoupling is configured to EXT (Parameter 160)
If emergency power (AMF) is enabled (mains failure)
following the "CLOSED TRANSIT." (
make-before-break/overlap synchronization) of the GCB
Before the GCB is closed to the dead busbar in the case of the breaker logic "OPEN TRANSIT." (break-
before-make/changeover)
Upon pressing the push-button "MCB OFF" or "GCB ON" (depending on the breaker logic which has been
configured) in operation mode MANUAL
Upon pressing the push-button "MCB OFF" or "GCB ON" (depending on the breaker logic which has been
configured) in operation mode LOAD TEST
Following the soft loading (interchange synchronization) of the MCB