Operation
6.28 Parking the Machine
66
Operator’s Manual | SM100 | 5100064108 | 08/2022 | [en-US]
6.28 Parking the Machine
Fig.51: Parking the machine
1. Park the machine on a level surface with the lift arm completely low-
ered.
2. If the machine is parked on a slope, position the front of the machine
downhill. If possible, tilt the attachment (such as a bucket) down so that
it digs into the ground.
3. Engage the parking brake.
4. Allow the engine to cool down at low idle for 5 minutes without any
load.
5. Turn the ignition key to the OFF position to stop the engine.
6. Step off the operator platform.
7. Chock the .
8. Make sure the parking brake pins are engaged (at least one).

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the AEM SM100 and is the answer not in the manual?

AEM SM100 Specifications

General IconGeneral
BrandAEM
ModelSM100
CategoryCompact Loader
LanguageEnglish