TT100 In-Line Viscometer Installation, Operation, Maintenance and Service Instructions
P/N M/97-520 2-1
Section 2 - Installation
Unpacking and Inspection
NOTE: Upon receipt, inspect the shipping carton and viscometer
components for shipping damage. Report any damage to the shipping
company immediately.
The shipping carton should contain the following components:
TT100 In-Line Viscometer
Torque Sensor Enclosure and Cable
Motor Controller Enclosure and Cable
Instruction Manual
Calibration Bars and Tools
Optional Equipment
NOTE: Make sure the calibration bars are kept in a safe place and
accessible for use during calibration.
Installation Requirements
NOTE: Refer to the TT100 In-Line Viscometer Specification sheet to
determine the configuration of the viscometer.
The TT100 In-Line Viscometer must be installed in a manner that will
optimize its performance. The installation requirements are:
Provide a continuous product stream to the viscometer with a
minimum time lag between changes in process and their effects on
the viscometer. This stream must be representative of other process
fluid.
Install the viscometer so that it is always full of fluid without air
pockets or voids. Upflow line mounting is recommended as shown
in Figure 2-1. Avoid pipe configurations which allow air or solids
to collect in the viscometer. The viscometer can only measure the
viscosity of fluids contained in the measuring annulus.