TT100 In-Line Viscometer Installation, Operation, Maintenance and Service Instructions
P/N M/97-520 3-1
Section 3 - Calibration
Introduction
The TT100 In-Line Viscometer is custom calibrated at the factory and
shipped ready for service. Brookfield Engineering Laboratories, Inc.
recommends that certain calibration procedures be performed after any of
the following events have occurred:
• Installation
• Disassembly and Cleaning
• Component Replacement
The flowcharts in Figures 3-1, 3-2, and 3-3 describe the appropriate
calibration procedures that should be performed after installation,
disassembly and cleaning, and component replacement.
CAUTION
The length of the sensing cable should not be changed. Contact Brookfield
Engineering Laboratories, Inc. for more information.
CAUTION
The viscometer must be empty of process fluid, clean, and free of obstruc-
tions before it can be calibrated. Refer to Section 5 - Maintenance and
perform the appropriate cleaning procedure for the process fluid applica-
tion.