Figure 33: Rear Right / Front Right
Step 5 Install 4 M5 nuts on the left and right side rack mounts.
Figure 34: M5 Nuts Installation
Step 6 Using a mechanical lift or scissors jack (not included) align the server at the correct height in the rack.
If a server lift is not available, you will need at least two people to lift the chassis into place.
Warning
The fully configured server weighs approximately 265 lbs. (120 kg)! Never attempt to lift the server by yourself! Instead,
use a lift, scissors jack, or some other device to lift and bear the weight of the server while you are installing or servicing
it. If you must lift or handle the server without mechanical assistance, use two or more people to lift and handle server.
Always use safe lifting practices when lifting or moving the server.
Step 7 Carefully slide the server into the rack, ensuring it aligns with the rails and position the server correctly within the rack.
Step 8 Ensure that the server is securely fastened with four M5 nuts on the left and right sides. Use a #2 screwdriver to tighten
the thumbscrews.
Cisco UCS C885A M8 Server Installation and Service Guide