Emerson Process Management GmbH & Co. OHG 3-1
X-STREAM X2FD
Instruction Manual
HASXMDE-IM-EX
01/2015
3
Startup
EXPLOSION HAZARD
Ensure all covers, plugs and housing parts are in place and secured properly
before supplying power and signal voltages!
Ensure all requirements given by the clarifi cation sheet for performing
gas analysis within a fl ameproof enclosure are considered BEFORE
supplying gases (
page S-10)!
The sheet also gives instructions for the sequence of supply-ing gases
during process and analyzer startup .
OPERATION AT LOW TEMPERATURES
When operating an instrument at temperatures below 0 °C (32 °F), do
NOT apply gas nor operate the internal pump before the warmup time has
elapsed!
Violation may result in condensation inside the gas paths or damaged
pump diaphragm!
Consider the related instructions in the X-STREAM X2 series manual!
Chapter 3
Startup
3.1 Final Check
Ensure that the analyzer has been installed
according to the descriptions in chapter 2,
and that all covers and doors are closed and
fastened.