MAINTENANCE MANUAL
Page 71-6
Effectivity: All
Edition 2 | Rev. 0
3. MAINTENANCE PRACTICES
A. Engine
Maintenance type: Heavy
Personnel qualification: Independent verification personnel qualified in accordance with
Part 66 or higher
Recommended tools and material:
Cable tie 4,8x368 As needed
Cable tie 2,5x99 As needed
Stainless lockwire ø 0,8 mm As needed
Adjustable pliers - 1 pc.
Hex key No. 5 1 pc.
Flat screwdriver - 1 pc.
Nippers - 1 pc.
Gripping pliers Cobra 1 pc.
Workshop crane - 1 pc. Load capacity min.
250 kg
Suspension straps - 3 pcs. Load capacity min.
250 kg
WARNING
BEFORE STARTING THE WORK, COOL DOWN THE
ENGINE UP TO THE AMBIENT TEMPERATURE. NON-
COMPLIANCE WITH THE PROCEDURE MAY RESULT IN
BURNS AND SCALDS.
SWITCH OFF THE IGNITION AND TAKE OUT THE KEY!
CAUTION
BEFORE THE ENGINE INSTALLATION, SUPPORT THE
REAR PART OF THE AIRCRAFT FUSELAGE BY MEANS OF
A SUITABLY DIMENSIONED SUPPORT (SECTION 07–02).
NOTE
By installation of suitable covers, blind plugs, etc., protect the
uncovered holes arisen as a result of removal or disconnecting,
so that water, impurities or foreign objects cannot enter them.
Observe the procedures relating to engine removal, as
specified by the engine manufacturer.