3.7 Connecting and Checking Office Battery to the CBP
This section includes the following subsections: Section
3.7.1 Connecting Office Battery to Circuit Breaker Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-31
3.7.2 Checking Battery Voltage at Circuit Breaker Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-33
If not done previously as part of an earlier FLASHWAVE 7500 installation, the office-battery
power cables must be connected to the CBP power input connectors. However, the
office-battery ends of the power cables must not be connected to the primary power source
until the CBP is completely installed.
Note: In this section, the term battery refers to the office DC power feed for the bay in which
the equipment is being mounted.
The CBP supports four separate battery/return power sources:
■
BATT A1/RTN A1
■
BATT A2/RTN A2
■
BATT B1/RTN B1
■
BATT B2/RTN B2
Each power input connection consists of a pair of parallel-wired, threaded studs. For example,
BATT A1 and RTN A1 both have two threaded studs.
An additional connector is provided for frame ground.
For additional details about the CBP, refer to Circuit Breaker Panel.
The following tools are required:
■
No. 1 Phillips screwdriver
■
7/16 inch socket wrench