5.10 Installing Power, Ground, and Alarm Cables
This procedure provides instructions for installing power, ground, and alarm cabling for
standard rack configurations.
It includes the following subprocedures: Procedure
5.10.1 Reference Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-24
5.10.2 Install Power, Ground, and Alarm Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-35
5.10.1 Reference Material
The cables and cable harnesses are listed in Table 5-1 [p. 5-24] and shown in Figure 5-10
[p. 5-25].
Note: Connections to the shelf power terminal strip should use copper conductors only.
Table 5-1: Power, Ground, and Alarm Cable Connections
(Extension Configuration)
Part Number Use Description Term Type Wire Gauge
HA15B-0001-C413 –48 V DC and
ground
5-wire rack/shelf power harness,
one set per shelf
10 AWG crimp
lugs
10 AWG
HA660-1106-T003 Rack alarms 6-connector daisy-chained alarm
harness, one connector per shelf
(CNA through CNF), one harness
per rack
D-sub 25-pin,
terminates with
wire-wrap at CBP
24 AWG
HA660-1102-T015 Shelf alarms Alarm cable from rack alarm cable
connector to shelf backplane alarm
connector, one per shelf
D-sub 25-pin,
CN1 at rack
alarm end, CN2
at shelf alarm end
24 AWG
PC15L-0001-C045 Frame ground Frame ground stranded wire cable
from rack to CBP, one per rack
Terminal lugs,
both ends,
installed
6 AWG, stranded