CHAPTER 5
Extension Configuration
Storing, Unpacking, and Inspecting Equipment
5-7
FLASHWAVE 7500 Release 6.1
Equipment Installation
Fujitsu and Fujitsu Customer Use Only
FNC-7500-0061-200
Issue 1, May 2009
5.4.3 Unpacking and Inspecting Equipment
This procedure provides guidelines for unpacking system equipment and ensuring the safe
arrival of all equipment. Fujitsu recommends that the installation team familiarize themselves
with the specific area where the installation is to be performed, examine the racks to be used,
and ensure that sufficient workspace is available to unpack equipment.
DANGER:
Do not attempt to handle and install the shelves without sufficient assistance. The
Extension shelf weighs approximately 48.5 lb (22 kg) empty (without fans). Equipped, the
Extension shelf weighs significantly more. Handling the equipment without sufficient
assistance may result in personal injury, damage to the equipment, or both.
WARNING:
Do not use the internal walls of any shelf as a lifting point or lift support. Doing so may
damage the plug-in unit rail support.
Step Task
1 Before unpacking the equipment, inspect the containers for signs of shipping damage. Claims
for shipping damage must be filed with the transportation company in accordance with their
published procedure.
2 Unpack and inventory individual system equipment components; however, leave all plug-in
units in their original, individual containers until they are installed during system turn-up.
When unpacking, use the checkoff list accompanying each shipment to determine that all
items are present before proceeding with the installation. If a shortage of any kind exists,
notify the appropriate Fujitsu representative.
3 Inspect the inside and outside of the shelves for damage.
4 Check for debris possibly lodged in each shelf backplane.
5 Update office records according to local procedures.
This procedure is complete.
Revision 1, June 2009