Chapter 2 Site Preparations 2 - 5
Site circuit breaker
It is recommended that the branch circuit breaker for the LOGIQ E10 be readily accessible.
Site power outlets
A dedicated AC power outlet must be within reach of the LOGIQ E10 without extension cords. Other
outlets adequate for the external peripherals, medical and test equipment needed to support this
LOGIQ E10 must also be present within 1 m (3.2 ft.) of the LOGIQ E10. Electrical installation must meet
all current local, state, and national electrical codes.
LOGIQ E10 power plug
If the LOGIQ E10 arrives without a power plug, or with the wrong plug, you must contact your GE dealer
or the installation engineer must supply what is locally required.
Power stability requirements
Voltage drop-out
Max 10 ms.
Power transients (all applications)
Less than 25% of nominal peak voltage for less than 1 ms for any type of transient, including line
frequency, synchronous, asynchronous, or aperiodic transients.
CAUTION
POWER OUTAGE MAY OCCUR.
THE LOGIQ E10 REQUIRES A DEDICATED SINGLE BRANCH CIRCUIT. TO AVOID CIRCUIT
OVERLOAD AND POSSIBLE LOSS OF CRITICAL CARE EQUIPMENT, MAKE SURE YOU DO NOT
HAVE ANY OTHER EQUIPMENT OPERATING ON THE SAME CIRCUIT.